NRW Reduction for the Municipal Water Utility ASKI in Adana, Turkey, ASKI financed – 2007 – 2008
In September 2007, ASKI appointed Berlinwasser International for six months duration to provide NRW service.
| Task |
| _ Establishment of pilot areas to demonstrate benefits from leak detection _ Production of water balances for pilot areas and service area _ Development of strategic plan to reduce REAL and APPARENT losses |
| ASKI is faced with issues that need the support of a qualified partner in order to develop sustainable solutions. These issues include: |
| _ Rapid growth in demand (currently serving for 1,3 m inhabitants with a water production rate of 500,000 m³/d and approx. 400.000 customer connections) _ Need to improve metering and billing _ An old distribution network regarding the house connections _ Non-Revenue Water of 65 % |
| The scope of work for BWI’s consulting service is as following: |
| _ Desktop Study _ Data collection and analysis _ IWA Water balance calculation and findings _ Establishment of pilot areas |
| Preparation of NRW strategic plan |
| _ Field Study _ Planned 4 pilot areas, each with approx. 3,000 house connections and an average monthly billing of 30,000 m³ _ Set-up pilot area _ Done step tests and leak detection/repair works _ Final report with recommendations and ASKI action plan |